Emergency round procurement (RMIPPP)

Some elements of this round are moving forward except for the floating gas component..

September 15, 2025

Gas electricity (floating) projects

Karpowership’s vessels projects were approved to provide 1,220MW of electricity capacity through the emergency’ procurement round. This came to an end when Eskom cancelled grid access for Karpowership after it was unable to meet the 31 December 2023 deadline for reaching financial close. HALTED: We stopped tracking this issue at end-June 2025. Following the failure…

read more >>