Summary
In November 2023, four bidders were announced as preferred bidders for four locations as part of the Battery Energy Storage Independent Power Procurement Programme (BESIPPP), while the fifth was announced on 2 April. The BESIPPP BW1 aims to procure 513MW site-agnostic battery storage. Four of these projects totalling 257MW have now reached financial close .
View DetailsIs it working?
The procurement has been effective; we await financial close from the winning bidders before construction and contribution to grid stability.
Actions
The government plans another bid window for battery storage, though this is running behind schedule.
Are there plans?
The DMRE has announced the preferred bidders and what remains is financial and commercial closure, construction and completion of the plants to be connected on line.
Is it on the agenda?
The DMRE initiated the procurement process in March 2023 and announced the preferred bidders in November 2023.
Goals
To procure battery storage capacity. The site-specific BESIPPPP Programme Bid Window 1 is part of a ministerial determination which aimed to procure 1,231MW by March 2024.
Summary
In November 2023, four bidders were announced as preferred bidders for four locations as part of the Battery Energy Storage Independent Power Procurement Programme (BESIPPP), while the fifth was announced on 2 April 2024. The BESIPPP BW1 aims to procure 513MW site-agnostic battery storage. Four of these projects totalling 257MW have now reached financial close and are under construction.
View DetailsIs it working?
None of the projects are yet connected to the grid. Four have achieved commercial close and have begun construction. The final, which would contribute 153 MW was expected to reach commercial close in mid 2025. We will continue to monitor implementation until the intended capacity is added to the grid.
Actions
The procurement is concluded and four projects (360MW) have reached commercial close in the quarter. However, according to the IPP Office, these projects are experiencing construction delays. The remaining projects are working toward commercial close, though they are struggling to finalise grid access agreements with Eskom.
Are there plans?
The DMRE announced the preferred bidders and what remains is financial and commercial closure, construction and completion of the plants to be connected to the grid.
Is it on the agenda?
The DMRE initiated the procurement process in March 2023 and announced the preferred bidders in November 2023.
Goals
To procure battery storage capacity through the IPP Office. The site-specific BESIPPPP Programme Bid Window 1 is part the first part of a ministerial determination which aimed to procure 1,231MW by March 2024. BW1 seeks to procure 513MW.
Summary
In November 2023, four bidders were announced as preferred bidders for four locations as part of the Battery Energy Storage Independent Power Procurement Programme (BESIPPP), while the fifth was announced on 2 April 2024. The BESIPPP BW1 aims to procure 513MW site-agnostic battery storage. Four of these projects totalling 257MW have now reached financial close and are under construction.
View DetailsIs it working?
None of the projects are yet connected to the grid. Four have achieved commercial close and have begun construction. The final, which would contribute 153 MW was expected to reach commercial close in mid 2025. We will continue to monitor implementation until the intended capacity is added to the grid.
Actions
The procurement is concluded and four projects (360MW) have reached commercial close in the quarter. However, according to the IPP Office, these projects are experiencing construction delays. The remaining projects are working toward commercial close, though they are struggling to finalise grid access agreements with Eskom.
Are there plans?
The DMRE announced the preferred bidders and what remains is financial and commercial closure, construction and completion of the plants to be connected to the grid.
Is it on the agenda?
The DMRE initiated the procurement process in March 2023 and announced the preferred bidders in November 2023.
Goals
To procure battery storage capacity through the IPP Office. The site-specific BESIPPPP Programme Bid Window 1 is part the first part of a ministerial determination which aimed to procure 1,231MW by March 2024. BW1 seeks to procure 513MW.
Summary
The site-specific BESIPPPP Programme Bid Window 1 is part of a ministerial determination which aimed to procure 1,231MW by March 2024. That deadline has been extended.
View DetailsIs it working?
The procurement has been effective but we wait to see if the winning bidders reach financial close and battery storage is contributing to grid stability.
Actions
The government plans another bid window for battery storage, though this is running behind schedule.
Are there plans?
The DMRE has announced the preferred bidders and what remains is the financial and commercial closure, construction and completion of the plants to be connected on line.
Is it on the agenda?
The DMRE initiated the procurement process in March 2023 and announced the preferred bidders in November.
Goals
In November 2023, four bidders were announced as preferred bidders for four locations as part of the Battery Energy Storage Independent Power Procurement (BESIPPP) Programme, while the fifth was announced on 2 April. The BESIPPP BW1 aimed to procure 513MW site-agnostic battery storage. The projects are now awaiting financial closure.
Summary
The site-specific BESIPPPP Programme Bid Window 1 is part of a ministerial determination which aimed to procure 1,231MW by March 2024. That deadline has been extended.
View DetailsIs it working?
The procurement has been effective; we await financial close from the winning bidders before construction and contribution to grid stability.
Actions
The government plans another bid window for battery storage, though this is running behind schedule.
Are there plans?
The DMRE has announced the preferred bidders and what remains is financial and commercial closure, construction and completion of the plants to be connected on line.
Is it on the agenda?
The DMRE initiated the procurement process in March 2023 and announced the preferred bidders in November.
Goals
In November 2023, four bidders were announced as preferred bidders for four locations as part of the Battery Energy Storage Independent Power Procurement Programme (BESIPPP), while the fifth was announced on 2 April. The BESIPPP BW1 aims to procure 513MW site-agnostic battery storage. The projects are now awaiting financial closure.
Summary
In November 2023, four bidders were announced as preferred bidders for four locations as part of the Battery Energy Storage Independent Power Procurement Programme (BESIPPP), while the fifth was announced on 2 April. The BESIPPP BW1 aims to procure 513MW site-agnostic battery storage. Four of these projects totalling 257MW have now reached financial close .
View DetailsIs it working?
The procurement has been effective; we await financial close from the winning bidders before construction and contribution to grid stability.
Actions
The government plans another bid window for battery storage, though this is running behind schedule.
Are there plans?
The DMRE has announced the preferred bidders and what remains is financial and commercial closure, construction and completion of the plants to be connected on line.
Is it on the agenda?
The DMRE initiated the procurement process in March 2023 and announced the preferred bidders in November 2023.
Goals
To procure battery storage capacity. The site-specific BESIPPPP Programme Bid Window 1 is part of a ministerial determination which aimed to procure 1,231MW by March 2024.
Summary
In November 2023, four bidders were announced as preferred bidders for four locations as part of the Battery Energy Storage Independent Power Procurement Programme (BESIPPP), while the fifth was announced on 2 April. The BESIPPP BW1 aims to procure 513MW site-agnostic battery storage. Four of these projects totalling 257MW have now reached financial close .
View DetailsIs it working?
The procurement has been effective; we await financial close from the winning bidders before construction and contribution to grid stability.
Actions
The government plans another bid window for battery storage, though this is running behind schedule.
Are there plans?
The DMRE has announced the preferred bidders and what remains is financial and commercial closure, construction and completion of the plants to be connected on line.
Is it on the agenda?
The DMRE initiated the procurement process in March 2023 and announced the preferred bidders in November 2023.
Goals
To procure battery storage capacity. The site-specific BESIPPPP Programme Bid Window 1 is part of a ministerial determination which aimed to procure 1,231MW by March 2024.
Summary
The DMRE has launched the second bid window (BW2) for the Battery Energy Storage Independent Power Producers Procurement Programme. The closing date for bidders was 29 August 2024, following the RFP release on 14 December 2023, The deadline for bids was extended from 30 April to 6 June 2024 and later to 29 August 2024. This extension took into consideration the timelines indicated by Eskom for the processing of CEL applications, as well as requests from bidders to allow more time for the preparation of their bid responses.
View DetailsIs it working?
To be determined. Bid submissions followed by financial close for the winners are the short-term goals, after which construction of plants and contributions to grid stability will determine substantive efficacy.
Actions
Announced financial closure of four projects worth 257MW.
Are there plans?
Preferred bidders were scheduled to be announced approximately three months after the bid submission deadline of 29 August 2024.
Is it on the agenda?
The government has issued a request for proposals on the IPPO website. The IPPO is responsible for managing the process.
Goals
To procure battery storage capacity.
Summary
The DMRE launched the second bid window (BW2) for the Battery Energy Storage Independent Power Producers Procurement Programme. The closing date for bidders was 29 August 2024, following the RFP release on 14 December 2023, The deadline for bids was extended from 30 April to 6 June 2024 and later to 29 August 2024. This extension took into consideration the timelines indicated by Eskom for the processing of cost estimate letters from Eskom which indicates the cost of connecting to the grid, as well as requests from bidders to allow more time for the preparation of their bid responses.
View DetailsIs it working?
None of the projects are yet connected to the grid. None have yet achieved commercial or financial close. We will continue to monitor implementation until the target capacity has been successfully added to the grid.
Actions
The bidding round was conducted and preferred bidders were announced on 23 December 2024. The IPP Office expects them to reach financial close in March 2026.
Are there plans?
The bid window was launched by government in 2023 and has been conducted in line with the wider plan for battery storage procurement, led by the IPP Office.
Is it on the agenda?
This second round followed quickly from the first in line with the ministerial determination that a total of 1,231 MW of battery storage capacity should be procured.
Goals
To procure battery storage capacity through the IPP Office. This second bid window followed quickly on BW1 of the BESIPPPP with a target of 615MW
Summary
The DMRE launched the second bid window (BW2) for the Battery Energy Storage Independent Power Producers Procurement Programme. The closing date for bidders was 29 August 2024, following the RFP release on 14 December 2023, The deadline for bids was extended from 30 April to 6 June 2024 and later to 29 August 2024. This extension took into consideration the timelines indicated by Eskom for the processing of cost estimate letters from Eskom which indicates the cost of connecting to the grid, as well as requests from bidders to allow more time for the preparation of their bid responses.
View DetailsIs it working?
None of the projects are yet connected to the grid. None have yet achieved commercial or financial close. We will continue to monitor implementation until the target capacity has been successfully added to the grid.
Actions
The bidding round was conducted and preferred bidders were announced on 23 December 2024. The IPP Office expects them to reach financial close in March 2026.
Are there plans?
The bid window was launched by government in 2023 and has been conducted in line with the wider plan for battery storage procurement, led by the IPP Office.
Is it on the agenda?
This second round followed quickly from the first in line with the ministerial determination that a total of 1,231 MW of battery storage capacity should be procured.
Goals
To procure battery storage capacity through the IPP Office. This second bid window followed quickly on BW1 of the BESIPPPP with a target of 615MW
Summary
On 14 December 2023, the DMRE launched the second bid window (BW2) for the Battery Energy Storage Independent Power Producers Procurement Programme. BW2 was launched in December last year and the deadline for bids has been extended from 30 April to 6 June 2024. This extension took into consideration the timelines indicated by Eskom for the processing of CEL applications, as well as requests from bidders to allow more time for the preparation of their bid responses. Potential bidders were informed of the new timelines in a briefing note that was communicated on 28 March.
View DetailsIs it working?
Bid submissions followed by financial close for the winners are the short-term goals, after which construction of plants and contributions to grid stability will determine substantive efficacy.
Actions
The DMRE and the IPPO have released a request for proposals to procure the 615MW of battery storage.
Are there plans?
Preferred bidders will be announced approximately three months after the bid submission deadline of 6 June 2024.
Is it on the agenda?
The government has issued a request for proposals on the IPPO website. The IPPO is responsible for managing the process.
Goals
The DMRE and the IPPO have issued a request for proposals to procure 615MW of battery storage capacity and ancillary services, in line with the power system services requirements as set out by the System Operator.
Summary
On 14 December 2023, the DMRE launched the second bid window (BW2) for the Battery Energy Storage Independent Power Producers Procurement Programme. The deadline for bids was extended from 30 April to 6 June 2024 and later to 29 August 2024 This extension took into consideration the timelines indicated by Eskom for the processing of CEL applications, as well as requests from bidders to allow more time for the preparation of their bid responses.
View DetailsIs it working?
To be determined - bid submissions followed by financial close for the winners are the short-term goals, after which construction of plants and contributions to grid stability will determine substantive efficacy.
Actions
The DMRE and the IPPO have released a request for proposals to procure the 615MW of battery storage.
Are there plans?
Preferred bidders will be announced approximately three months after the bid submission deadline of 29 August 2024.
Is it on the agenda?
The government has issued a request for proposals on the IPPO website. The IPPO is responsible for managing the process.
Goals
The DMRE and the IPPO have issued a request for proposals to procure 615MW of battery storage capacity and ancillary services, in line with the power system services requirements as set out by the System Operator.
Summary
The DMRE has launched the second bid window (BW2) for the Battery Energy Storage Independent Power Producers Procurement Programme. The closing date for bidders was 29 August 2024, following the RFP release on 14 December 2023, The deadline for bids was extended from 30 April to 6 June 2024 and later to 29 August 2024. This extension took into consideration the timelines indicated by Eskom for the processing of CEL applications, as well as requests from bidders to allow more time for the preparation of their bid responses.
View DetailsIs it working?
To be determined. Bid submissions followed by financial close for the winners are the short-term goals, after which construction of plants and contributions to grid stability will determine substantive efficacy.
Actions
Announced financial closure of four projects worth 257MW.
Are there plans?
Preferred bidders were scheduled to be announced approximately three months after the bid submission deadline of 29 August 2024.
Is it on the agenda?
The government has issued a request for proposals on the IPPO website. The IPPO is responsible for managing the process.
Goals
To procure battery storage capacity.
Summary
The DMRE has launched the second bid window (BW2) for the Battery Energy Storage Independent Power Producers Procurement Programme. The closing date for bidders was 29 August 2024, following the RFP release on 14 December 2023, The deadline for bids was extended from 30 April to 6 June 2024 and later to 29 August 2024. This extension took into consideration the timelines indicated by Eskom for the processing of CEL applications, as well as requests from bidders to allow more time for the preparation of their bid responses.
View DetailsIs it working?
To be determined. Bid submissions followed by financial close for the winners are the short-term goals, after which construction of plants and contributions to grid stability will determine substantive efficacy.
Actions
Announced financial closure of four projects worth 257MW.
Are there plans?
Preferred bidders were scheduled to be announced approximately three months after the bid submission deadline of 29 August 2024.
Is it on the agenda?
The government has issued a request for proposals on the IPPO website. The IPPO is responsible for managing the process.
Goals
To procure battery storage capacity.
Summary
BESIPPPP Bid Window 3 RFP was released to the market on 28 March 2024, with a bid submission deadline of 31 July 2024 that was later revised to 31 October 2024. The preferred bidder announcement is targeted for approximately three months after the bid submission date and financial close will be approximately six months post the preferred bidder announcement.
View DetailsIs it working?
To be determined - bid submissions followed by financial close for the winners are the short-term goals, after which construction of plants and contributions to grid stability will determine substantive efficacy.
Actions
The DMRE and the IPPO have released a request for proposals to procure the 615MW of battery storage.
Are there plans?
Preferred bidders will be announced approximately three months after the bid submission deadline of 31 October 2024.
Is it on the agenda?
The government has issued a request for proposals on the IPPO website. The IPPO is responsible for managing the process.
Goals
The BESIPPPP BW 3 RFP calls for proposals to be submitted for a total of 616 MW / 2,464 MWh of battery energy storage Projects allocated to five pre-selected substation sites identified by Eskom. The five sites are Harvard, Leander, Theseus, Everest and Merapi substations and are all located in the Free State.
Summary
BESIPPPP Bid Window 3 RFP was released to the market on 28 March 2024, with a bid submission deadline of 31 July 2024 that was later revised to 31 October 2024 This third round follows the first two rounds for BESS which have been held in quick succession. It aimed to procure 616MW of battery energy storage capacity at five pre-selected substations identified by Eskom. The preferred bidders were announced on 30 May 2025 with a capacity in line with the bid window target. Financial close was scheduled for approximately six months post the preferred bidder announcement.
View DetailsIs it working?
The benefits from this bid window of a more stable energy supply will likely be felt in 2028/29.
Actions
Actions completed.
Are there plans?
Financial close is scheduled for end-October 2025.
Is it on the agenda?
It has ibeen successfully completed.
Goals
The BESIPPPP BW 3 RFP inteded to generate a total of 616MW of battery energy storage with projects allocated to five pre-selected substation sites identified by Eskom: Harvard, Leander, Theseus, Everest and Merapi substations, are all located in the Free State..
Summary
BESIPPPP Bid Window 3 RFP was released to the market on 28 March 2024, with a bid submission deadline of 31 July 2024 that was later revised to 31 October 2024 This third round follows the first two rounds for BESS which have been held in quick succession. It aimed to procure 616MW of battery energy storage capacity at five pre-selected substations identified by Eskom. The preferred bidders were announced on 30 May 2025 with a capacity in line with the bid window target. Financial close was scheduled for approximately six months post the preferred bidder announcement.
View DetailsIs it working?
The benefits from this bid window of a more stable energy supply will likely be felt in 2028/29.
Actions
Actions completed.
Are there plans?
Financial close is scheduled for end-October 2025.
Is it on the agenda?
It has ibeen successfully completed.
Goals
The BESIPPPP BW 3 RFP inteded to generate a total of 616MW of battery energy storage with projects allocated to five pre-selected substation sites identified by Eskom: Harvard, Leander, Theseus, Everest and Merapi substations, are all located in the Free State..
Is it working?
0.00
Actions
0.00
Are there plans?
0.00
Is it on the agenda?
0.00
Goals
0.00
Summary
BESIPPPP Bid Window 3 RFP was released to the market on 28 March 2024, with bid submission on 31 July 2024 that was later revised to 31 October 2024. The preferred bidder announcement is targeted approximately three (3) months post the bid submission date and financial close will be approximately six (6) months post the preferred bidder announcement.
View DetailsIs it working?
To be determined - bid submissions followed by financial close for the winners are the short-term goals, after which construction of plants and contributions to grid stability will determine substantive efficacy.
Actions
The DMRE and the IPPO have released a request for proposals to procure the 615MW of battery storage.
Are there plans?
Preferred bidders will be announced approximately three months after the bid submission deadline of 31 October 2024.
Is it on the agenda?
The government has issued a request for proposals on the IPPO website. The IPPO is responsible for managing the process.
Goals
The BESIPPPP BW 3 RFP calls for proposals to be submitted for a total of 616 MW / 2,464 MWh of Battery Energy Storage Projects allocated to five (5) pre-selected substation sites identified by Eskom. The five sites are Harvard, Leander, Theseus, Everest, and Merapi substations and are all located in the Free State Province.
Summary
BESIPPPP Bid Window 3 RFP was released to the market on 28 March 2024, with a bid submission deadline of 31 July 2024 that was later revised to 31 October 2024. The preferred bidder announcement is targeted for approximately three months after the bid submission date and financial close will be approximately six months post the preferred bidder announcement.
View DetailsIs it working?
To be determined - bid submissions followed by financial close for the winners are the short-term goals, after which construction of plants and contributions to grid stability will determine substantive efficacy.
Actions
The DMRE and the IPPO have released a request for proposals to procure the 615MW of battery storage.
Are there plans?
Preferred bidders will be announced approximately three months after the bid submission deadline of 31 October 2024.
Is it on the agenda?
The government has issued a request for proposals on the IPPO website. The IPPO is responsible for managing the process.
Goals
The BESIPPPP BW 3 RFP calls for proposals to be submitted for a total of 616 MW / 2,464 MWh of battery energy storage Projects allocated to five pre-selected substation sites identified by Eskom. The five sites are Harvard, Leander, Theseus, Everest and Merapi substations and are all located in the Free State.
Summary
BESIPPPP Bid Window 3 RFP was released to the market on 28 March 2024, with a bid submission deadline of 31 July 2024 that was later revised to 31 October 2024. The preferred bidder announcement is targeted for approximately three months after the bid submission date and financial close will be approximately six months post the preferred bidder announcement.
View DetailsIs it working?
To be determined - bid submissions followed by financial close for the winners are the short-term goals, after which construction of plants and contributions to grid stability will determine substantive efficacy.
Actions
The DMRE and the IPPO have released a request for proposals to procure the 615MW of battery storage.
Are there plans?
Preferred bidders will be announced approximately three months after the bid submission deadline of 31 October 2024.
Is it on the agenda?
The government has issued a request for proposals on the IPPO website. The IPPO is responsible for managing the process.
Goals
The BESIPPPP BW 3 RFP calls for proposals to be submitted for a total of 616 MW / 2,464 MWh of battery energy storage Projects allocated to five pre-selected substation sites identified by Eskom. The five sites are Harvard, Leander, Theseus, Everest and Merapi substations and are all located in the Free State.
Summary
The Gas IPP Procurement Programme determination was gazetted on 25 September 2020 to procure 3,000MW of new generation capacity from gas technologies. The DMRE launched the request for proposals for the first gas IPP BW1 on 14 December 2023 to procure 2,000MW. The IRP 2023 allocates 7.2GW-8.6GW of gas-to-power capacity.
View DetailsIs it working?
This process is still in the early stages, being the first procurement of gas-fired power from independent producers. The first main test will be achieving financial and commercial close, which will reflect whether or not such projects are financially viable. One problem to overcome is in supplying gas to these power stations as the infrastructure does not exist and that takes time to develop – and it is expensive.
Actions
RFPs have been issued but deadline extended to 2025,
Are there plans?
Bidders must be capable of achieving commercial operations within 36 months after commercial close. Gas projects are therefore scheduled to come on stream in late 2026/early 2027.
Is it on the agenda?
The former DMRE issued the request for proposals in December 2023 and a deadline for submission was set for 30 August 2024, which was later extended to 2025 because the department is examining a few of the RFP's clauses that registered bidders brought up during the RFP's planned clarification process. The department will need to confer with important stakeholders to resolve these issues. Investigating and considering the issues brought up during the clarification process is in progress. If necessary, the department will revise the RFP by issuing briefing notes.
Goals
The gas BW1 aims to procure 2,000MW of new generation capacity, ancillary services and energy output to be produced from gas-fired power generation projects. This round specifically targets land-based electricity generation facilities utilising natural gas, located within South Africa.
Summary
The Gas IPP Procurement Programme determination was gazetted on 25 September 2020 to procure 3,000MW of new generation capacity from gas technologies. The DMRE launched the request for proposals for the first gas IPP BW1 on 14 December 2023 to procure 2,000MW. However, an amendment to the RFP is currently underway and a bid submission date is still to be confirmed.
View DetailsIs it working?
The procurment process is still underway, being the first procurement of gas-fired power from independent producers. The first main test will be achieving financial and commercial close, which will reflect whether or not such projects are financially viable. One problem to overcome is in supplying gas to these power stations as the infrastructure does not exist and that takes time to develop – and it is expensive. There may also be environmental objections to the further exploitation of fossil fuels.
Actions
The bidding round has not yet been concluded with the latest bid submission date of 31 October 2025 (having been postponed twice since the original date of 30 August 2024). Bidders must be capable of achieving commercial operations within 36 months after commercial close. Gas projects are therefore scheduled to come on stream in late 2026/early 2027.
Are there plans?
The former DMRE issued the request for proposals in December 2023 and a deadline for submission was set for 30 August 2024, which was later extended to 25 March 2025. However, this has been further delayed because the department is examining a few of the RFP's clauses that registered bidders brought up during the RFP's planned clarification process. In February 2025, the department announced a bid submission date of 31 October 2025.
Is it on the agenda?
Gas procurement has been on the agenda since at least 2020, but progress has been slow.
Goals
The gas BW1 aims to procure 2,000MW of new generation capacity, ancillary services and energy output to be produced from gas-fired power generation projects. This round specifically targets land-based electricity generation facilities utilising natural gas, located within South Africa. A second BW is intended to procure 1,000MW specifically from a single gas-fired power project in Coega, but is still in design phase (see BW2).
Summary
The Gas IPP Procurement Programme determination was gazetted on 25 September 2020 to procure 3,000MW of new generation capacity from gas technologies. The DMRE launched the request for proposals for the first gas IPP BW1 on 14 December 2023 to procure 2,000MW. However, an amendment to the RFP is currently underway and a bid submission date is still to be confirmed.
View DetailsIs it working?
The procurment process is still underway, being the first procurement of gas-fired power from independent producers. The first main test will be achieving financial and commercial close, which will reflect whether or not such projects are financially viable. One problem to overcome is in supplying gas to these power stations as the infrastructure does not exist and that takes time to develop – and it is expensive. There may also be environmental objections to the further exploitation of fossil fuels.
Actions
The bidding round has not yet been concluded with the latest bid submission date of 31 October 2025 (having been postponed twice since the original date of 30 August 2024). Bidders must be capable of achieving commercial operations within 36 months after commercial close. Gas projects are therefore scheduled to come on stream in late 2026/early 2027.
Are there plans?
The former DMRE issued the request for proposals in December 2023 and a deadline for submission was set for 30 August 2024, which was later extended to 25 March 2025. However, this has been further delayed because the department is examining a few of the RFP's clauses that registered bidders brought up during the RFP's planned clarification process. In February 2025, the department announced a bid submission date of 31 October 2025.
Is it on the agenda?
Gas procurement has been on the agenda since at least 2020, but progress has been slow.
Goals
The gas BW1 aims to procure 2,000MW of new generation capacity, ancillary services and energy output to be produced from gas-fired power generation projects. This round specifically targets land-based electricity generation facilities utilising natural gas, located within South Africa. A second BW is intended to procure 1,000MW specifically from a single gas-fired power project in Coega, but is still in design phase (see BW2).
Summary
The Gas IPP Procurement Programme determination was gazetted on 25 September 2020 to procure 3,000MW of new generation capacity from gas technologies. The DMRE launched the request for proposals for the first gas IPP BW1 on 14 December 2023 to procure 2,000MW. The IRP 2023 allocates 7.2GW-8.6GW of gas-to-power capacity.
View DetailsIs it working?
This process is still in the early stages, being the first procurement of gas-fired power from independent producers. The first main test will be achieving financial and commercial close, which will reflect whether or not such projects are financially viable. One problem to overcome is in supplying gas to these power stations as the infrastructure does not exist and that takes time to develop – and it’s expensive.
Actions
RFPs issued.
Are there plans?
Bidders must be capable of achieving commercial operations within 36 months after commercial close. Gas projects are therefore scheduled to come on stream in late 2026/early 2027.
Is it on the agenda?
The DMRE issued the request for proposals in December 2023 with a deadline for submission of 30 August 2024.
Goals
The gas BW1 aims to procure 2,000MW of new generation capacity, ancillary services and energy output to be produced from gas-fired power generation projects. This round specifically targets land-based electricity generation facilities utilising natural gas, located within South Africa.
Summary
The Gas IPP Procurement Programme determination was gazetted on 25 September 2020 to procure 3,000MW of new generation capacity from gas technologies. The DMRE launched the request for proposals for the first gas IPP BW1 on 14 December 2023 to procure 2,000MW. The IRP 2023 allocates 7.2GW-8.6GW of gas-to-power capacity.
View DetailsIs it working?
This process is still in the early stages, being the first procurement of gas-fired power from independent producers. The first main test will be achieving financial and commercial close, which will reflect whether or not such projects are financially viable. One problem to overcome is in supplying gas to these power stations as the infrastructure does not exist and that takes time to develop – and it’s expensive.
Actions
RFPs have been issued.
Are there plans?
Bidders must be capable of achieving commercial operations within 36 months after commercial close. Gas projects are therefore scheduled to come on stream in late 2026/early 2027.
Is it on the agenda?
The DMRE issued the request for proposals in December 2023 and a deadline for submission was set for 30 August 2024. The deadline will likely be pushed out because the DMRE is examining a few of the RFP's clauses that registered bidders brought up during the RFP's planned clarification process. The Department will need to confer with important stakeholders to resolve these issues. Investigating and considering the issues brought up during the clarification process is in progress. If necessary, the department will revise the RFP by issuing briefing notes.
Goals
The gas BW1 aims to procure 2,000MW of new generation capacity, ancillary services and energy output to be produced from gas-fired power generation projects. This round specifically targets land-based electricity generation facilities utilising natural gas, located within South Africa.
Summary
The Gas IPP Procurement Programme determination was gazetted on 25 September 2020 to procure 3,000MW of new generation capacity from gas technologies. The DMRE launched the request for proposals for the first gas IPP BW1 on 14 December 2023 to procure 2,000MW. The IRP 2023 allocates 7.2GW-8.6GW of gas-to-power capacity.
View DetailsIs it working?
This process is still in the early stages, being the first procurement of gas-fired power from independent producers. The first main test will be achieving financial and commercial close, which will reflect whether or not such projects are financially viable. One problem to overcome is in supplying gas to these power stations as the infrastructure does not exist and that takes time to develop – and it is expensive.
Actions
RFPs have been issued but deadline extended to 2025,
Are there plans?
Bidders must be capable of achieving commercial operations within 36 months after commercial close. Gas projects are therefore scheduled to come on stream in late 2026/early 2027.
Is it on the agenda?
The former DMRE issued the request for proposals in December 2023 and a deadline for submission was set for 30 August 2024, which was later extended to 2025 because the department is examining a few of the RFP's clauses that registered bidders brought up during the RFP's planned clarification process. The department will need to confer with important stakeholders to resolve these issues. Investigating and considering the issues brought up during the clarification process is in progress. If necessary, the department will revise the RFP by issuing briefing notes.
Goals
The gas BW1 aims to procure 2,000MW of new generation capacity, ancillary services and energy output to be produced from gas-fired power generation projects. This round specifically targets land-based electricity generation facilities utilising natural gas, located within South Africa.
Summary
The Gas IPP Procurement Programme determination was gazetted on 25 September 2020 to procure 3,000MW of new generation capacity from gas technologies. The DMRE launched the request for proposals for the first gas IPP BW1 on 14 December 2023 to procure 2,000MW. The IRP 2023 allocates 7.2GW-8.6GW of gas-to-power capacity.
View DetailsIs it working?
This process is still in the early stages, being the first procurement of gas-fired power from independent producers. The first main test will be achieving financial and commercial close, which will reflect whether or not such projects are financially viable. One problem to overcome is in supplying gas to these power stations as the infrastructure does not exist and that takes time to develop – and it is expensive.
Actions
RFPs have been issued but deadline extended to 2025,
Are there plans?
Bidders must be capable of achieving commercial operations within 36 months after commercial close. Gas projects are therefore scheduled to come on stream in late 2026/early 2027.
Is it on the agenda?
The former DMRE issued the request for proposals in December 2023 and a deadline for submission was set for 30 August 2024, which was later extended to 2025 because the department is examining a few of the RFP's clauses that registered bidders brought up during the RFP's planned clarification process. The department will need to confer with important stakeholders to resolve these issues. Investigating and considering the issues brought up during the clarification process is in progress. If necessary, the department will revise the RFP by issuing briefing notes.
Goals
The gas BW1 aims to procure 2,000MW of new generation capacity, ancillary services and energy output to be produced from gas-fired power generation projects. This round specifically targets land-based electricity generation facilities utilising natural gas, located within South Africa.
Summary
Following environmental authorisaion approval by Minister Barbara Creecy in 2022 for the 2,000MW Phakwe gas power plant in Richards Bay Industrial Development Zone, two civil society groups, Groundwork and South Durban Community Environmental Alliance (SDCEA), represented by the Centre for Environmental Rights (CER), filed for judicial review.
View DetailsIs it working?
Plan is stalled pending the legal challenges.
Actions
Process being held up by legal challenges.
Are there plans?
Process being held up by legal challenges. Eskom has plans to set up a 3,000MW gas to power plant in Richard's Bay
Is it on the agenda?
The power plant is a 2,000MW facility.
Goals
The Richards Bay gas-to-power project faces environmental challenges.
Summary
Following environmental authorisation approval by Minister Barbara Creecy in 2022 for the 2,000MW Phakwe gas power plant in Richards Bay Industrial Development Zone, two civil society groups, Groundwork and South Durban Community Environmental Alliance (SDCEA), represented by the Centre for Environmental Rights (CER), filed for judicial review.
View DetailsIs it working?
Plan is stalled pending the legal challenges. Construction has not begun and grid connection is some way off.
Actions
The project faces legal obstacles after civil society groups took action in March 2024. The case has yet to resolve and we have been unable to determine when judgement may emerge.
Are there plans?
Plans for the project have unfolded over several years, most recently by including it into the gas IPP bid window. However, the process is now being held up by legal challenges by environmental civil society groups. In the meantime Eskom has plans to set up a 3,000MW gas to power plant in Richard's Bay that may make Phakwe redundant, at least at the 2,000MW capacity.
Is it on the agenda?
The plant has been on the agenda for some time, with initial environmental authorisation granted in 2016.
Goals
Construct and connect a 2,000MW gas-fired power station in Richard's Bay.
Summary
Following environmental authorisation approval by Minister Barbara Creecy in 2022 for the 2,000MW Phakwe gas power plant in Richards Bay Industrial Development Zone, two civil society groups, Groundwork and South Durban Community Environmental Alliance (SDCEA), represented by the Centre for Environmental Rights (CER), filed for judicial review.
View DetailsIs it working?
Plan is stalled pending the legal challenges. Construction has not begun and grid connection is some way off.
Actions
The project faces legal obstacles after civil society groups took action in March 2024. The case has yet to resolve and we have been unable to determine when judgement may emerge.
Are there plans?
Plans for the project have unfolded over several years, most recently by including it into the gas IPP bid window. However, the process is now being held up by legal challenges by environmental civil society groups. In the meantime Eskom has plans to set up a 3,000MW gas to power plant in Richard's Bay that may make Phakwe redundant, at least at the 2,000MW capacity.
Is it on the agenda?
The plant has been on the agenda for some time, with initial environmental authorisation granted in 2016.
Goals
Construct and connect a 2,000MW gas-fired power station in Richard's Bay.
Summary
Two civil society groups, Groundwork and South Durban Community Environmental Alliance (SDCEA), represented by the Centre for Environmental Rights (CER), have filed for judicial review against the decision by Minister Barbara Creecy to approve the environmental authorisation for the proposed 2,000MW Phakwe gas power plant in Richards Bay Industrial Development Zone.
View DetailsIs it working?
Not yet
Actions
0.00
Are there plans?
0.00
Is it on the agenda?
To procure 2,000MW gas to power
Goals
There are environmental challenges against the Richards bay gas-to-power project
Summary
Two civil society groups, Groundwork and South Durban Community Environmental Alliance (SDCEA), represented by the Centre for Environmental Rights (CER), have filed for judicial review against the decision by Minister Barbara Creecy to approve the environmental authorisation for the proposed 2,000MW Phakwe gas power plant in Richards Bay Industrial Development Zone.
View DetailsIs it working?
Not yet.
Actions
Process being held up by legal challenges.
Are there plans?
Process being held up by legal challenges.
Is it on the agenda?
The power plant is a 2,000MW facility.
Goals
The Richards Bay gas-to-power project faces environmental challenges.
Summary
Following environmental authorisaion approval by Minister Barbara Creecy in 2022 for the 2,000MW Phakwe gas power plant in Richards Bay Industrial Development Zone, two civil society groups, Groundwork and South Durban Community Environmental Alliance (SDCEA), represented by the Centre for Environmental Rights (CER), filed for judicial review.
View DetailsIs it working?
Plan is stalled pending the legal challenges.
Actions
Process being held up by legal challenges.
Are there plans?
Process being held up by legal challenges. Eskom has plans to set up a 3,000MW gas to power plant in Richard's Bay
Is it on the agenda?
The power plant is a 2,000MW facility.
Goals
The Richards Bay gas-to-power project faces environmental challenges.
Summary
Following environmental authorisaion approval by Minister Barbara Creecy in 2022 for the 2,000MW Phakwe gas power plant in Richards Bay Industrial Development Zone, two civil society groups, Groundwork and South Durban Community Environmental Alliance (SDCEA), represented by the Centre for Environmental Rights (CER), filed for judicial review.
View DetailsIs it working?
Plan is stalled pending the legal challenges.
Actions
Process being held up by legal challenges.
Are there plans?
Process being held up by legal challenges. Eskom has plans to set up a 3,000MW gas to power plant in Richard's Bay
Is it on the agenda?
The power plant is a 2,000MW facility.
Goals
The Richards Bay gas-to-power project faces environmental challenges.
Summary
On 22 June 2023, the cabinet signed an agreement for Mozambique to supply South Africa with 100MW of electricity within three months of the power purchase agreement. Three months later, the Mozambican government said that it wanted answers from President Cyril Ramaphosa's administration as to why there had been no movement from Eskom on the 100MW of electricity that the country had offered to South Africa to help alleviate load shedding.
View DetailsIs it working?
Not effective. The deal never took off and the Mozambican government has been seeking answers.
Actions
None.
Are there plans?
The plans have stalled.
Is it on the agenda?
The plan was announced at the National Assembly by the electricity ministry to procure 100MW from Mozambique but the plan did not move forward.
Goals
To procure cross-border electricity to assist in alleviating loadshedding impacts. Electricity minister Ramokgopa announced that there was an agreement in place between Mozambique and South Africa for the supply of 100MW of electricity but this has not moved forward.
Summary
On 22 June 2023, the cabinet signed an agreement for Mozambique to supply South Africa with 100MW of electricity within three months of the power purchase agreement. Three months later, the Mozambican government said that it wanted answers from President Cyril Ramaphosa's administration as to why there had been no movement from Eskom on the 100MW of electricity that the country had offered to South Africa to help alleviate load shedding. HALTED We stopped tracking this reform at end-June 2025 as it has been abandoned as a reform deliverable.
View DetailsIs it working?
No. The deal never pogressed beyond the initial agreement that was announced. The Mozambican government has been seeking answers and we believe the proposed deliverable has been abandoned by government. We therefore see this as a halted reform.
Actions
No actions have been taken to date to contribute Mozambican supply to the grid.
Are there plans?
It is not clear that concrete plans to implement the agreement to purchase 100MW were ever developed.
Is it on the agenda?
The agreement was announced at the National Assembly in 2023 by the electricity ministry to procure 100MW from Mozambique.
Goals
To procure cross-border electricity to assist in alleviating loadshedding impacts. Electricity minister Ramokgopa announced that there was an agreement in place between Mozambique and South Africa for the supply of 100MW of electricity.
Summary
On 22 June 2023, the cabinet signed an agreement for Mozambique to supply South Africa with 100MW of electricity within three months of the power purchase agreement. Three months later, the Mozambican government said that it wanted answers from President Cyril Ramaphosa's administration as to why there had been no movement from Eskom on the 100MW of electricity that the country had offered to South Africa to help alleviate load shedding. HALTED We stopped tracking this reform at end-June 2025 as it has been abandoned as a reform deliverable.
View DetailsIs it working?
No. The deal never pogressed beyond the initial agreement that was announced. The Mozambican government has been seeking answers and we believe the proposed deliverable has been abandoned by government. We therefore see this as a halted reform.
Actions
No actions have been taken to date to contribute Mozambican supply to the grid.
Are there plans?
It is not clear that concrete plans to implement the agreement to purchase 100MW were ever developed.
Is it on the agenda?
The agreement was announced at the National Assembly in 2023 by the electricity ministry to procure 100MW from Mozambique.
Goals
To procure cross-border electricity to assist in alleviating loadshedding impacts. Electricity minister Ramokgopa announced that there was an agreement in place between Mozambique and South Africa for the supply of 100MW of electricity.
Summary
On 22 June 2023, the cabinet signed an agreement for Mozambique to supply South Africa with 100MW of electricity within three months of the power purchase agreement. Three months later, the Mozambican government said that it wanted answers from President Cyril Ramaphosa's administration as to why there had been no movement from Eskom on the 100MW of electricity that the country had offered to South Africa to help alleviate load shedding.
View DetailsIs it working?
Not effective - The deal never took off and the Mozambican government has been seeking answers.
Actions
None
Are there plans?
No Plans as this reform is stuck .
Is it on the agenda?
The plan was announced at the National Assembly by the electricity ministry to procure 100MW from Mozambique but the plan did not move forward
Goals
Electricity minister Ramokgopa announced that there was an agreement in place between Mozambique and South Africa for the supply of 100MW of electricity but this has not moved forward.
Summary
On 22 June 2023, the cabinet signed an agreement for Mozambique to supply South Africa with 100MW of electricity within three months of the power purchase agreement. Three months later, the Mozambican government said that it wanted answers from President Cyril Ramaphosa's administration as to why there had been no movement from Eskom on the 100MW of electricity that the country had offered to South Africa to help alleviate load shedding.
View DetailsIs it working?
Not effective - The deal never took off and the Mozambican government has been seeking answers.
Actions
None
Are there plans?
No Plans as this reform is stuck .
Is it on the agenda?
The plan was announced at the National Assembly by the electricity ministry to procure 100MW from Mozambique but the plan did not move forward
Goals
Electricity minister Ramokgopa announced that there was an agreement in place between Mozambique and South Africa for the supply of 100MW of electricity but this has not moved forward.
Summary
On 22 June 2023, the cabinet signed an agreement for Mozambique to supply South Africa with 100MW of electricity within three months of the power purchase agreement. Three months later, the Mozambican government said that it wanted answers from President Cyril Ramaphosa's administration as to why there had been no movement from Eskom on the 100MW of electricity that the country had offered to South Africa to help alleviate load shedding.
View DetailsIs it working?
Not effective. The deal never took off and the Mozambican government has been seeking answers.
Actions
None.
Are there plans?
The plans have stalled.
Is it on the agenda?
The plan was announced at the National Assembly by the electricity ministry to procure 100MW from Mozambique but the plan did not move forward.
Goals
To procure cross-border electricity to assist in alleviating loadshedding impacts. Electricity minister Ramokgopa announced that there was an agreement in place between Mozambique and South Africa for the supply of 100MW of electricity but this has not moved forward.
Summary
On 22 June 2023, the cabinet signed an agreement for Mozambique to supply South Africa with 100MW of electricity within three months of the power purchase agreement. Three months later, the Mozambican government said that it wanted answers from President Cyril Ramaphosa's administration as to why there had been no movement from Eskom on the 100MW of electricity that the country had offered to South Africa to help alleviate load shedding.
View DetailsIs it working?
Not effective. The deal never took off and the Mozambican government has been seeking answers.
Actions
None.
Are there plans?
The plans have stalled.
Is it on the agenda?
The plan was announced at the National Assembly by the electricity ministry to procure 100MW from Mozambique but the plan did not move forward.
Goals
To procure cross-border electricity to assist in alleviating loadshedding impacts. Electricity minister Ramokgopa announced that there was an agreement in place between Mozambique and South Africa for the supply of 100MW of electricity but this has not moved forward.
Summary
On 14 December 2023, the IPPO announced the release of the BW7 procurement round that seeks to procure 5GW of new renewables through 3.2GW of wind and 1.8GW of solar energy. The IPPO received 48 onshore wind and solar PV proposals totaling 10,218 MW).
View DetailsIs it working?
The bid window is in process with bid being assessed.
Actions
RFP Closed
Are there plans?
The RFP was released in December and closed on 15 August 2024.
Is it on the agenda?
This bid window seeks to procure 5GW of new renewables through 3.2GW of wind and 1.8GW of solar energy.
Goals
To increase renewable energy procurement through REIPPPP
Summary
On 14 December 2023, the IPPO announced the release of the BW7 procurement round that seeks to procure 5GW of new renewables through 3.2GW of wind and 1.8GW of solar energy with an initial bid submission date of April 2024, that was subsequently revised to 15 August 2024. The IPPO received 48 onshore wind and solar PV proposals totalling 10,218MW, but announced successful bidders for only 1,760MW of solar (not one wind bid was successful). The department in July 2025 also announced an additional 1,290 MW of solar projects as preferred bidders. We now await commercial and financial close of these projects.
View DetailsIs it working?
We await financial close from the winning bidders before construction and contribution to grid stability. While the bid window is never going to achieve its initial targets, we will continue to monitor those projects that were selected until they are contributing to the grid before changing the status of this delivery item to halted. Projects are expected to join the grid in October 2027 at the earliest.
Actions
All of the required actions for the BW7 round have been implemented, however the bid window failed to achieve its initial capacity target with only 54% of the capacity available from the preferred bidders. We now await the preferred bidders to conclude commercial and financial close and begin construction. Additional solar PV preferred bidders were announced in July to make up the shortfall of wind projects, with more expected in August to close the gap on the round's targeted MW.
Are there plans?
Yes, in line with IPP Office's bid window approach, the RFP was released in December 2023 and closed on 15 August 2024 after being extended from April. Preferred bidders were announced in December 2024. The delays were due to grid access constraints that made it difficult for some projects to secure access agreements with Eskom.
Is it on the agenda?
The procurement process for Bid Window 7 was launched by the IPP Office in December 2023 and Electricity and energy Minister Kgosientsho Ramokgopa announced preferred bidders a year later.
Goals
To increase renewable energy procurement through Renewable Energy Independent Power Producer's Programme, BW7 had a total 5,000MW capacity target, which if successful would make it the largest REIPPP round to date.
Summary
On 14 December 2023, the IPPO announced the release of the BW7 procurement round that seeks to procure 5GW of new renewables through 3.2GW of wind and 1.8GW of solar energy with an initial bid submission date of April 2024, that was subsequently revised to 15 August 2024. The IPPO received 48 onshore wind and solar PV proposals totalling 10,218MW, but announced successful bidders for only 1,760MW of solar (not one wind bid was successful). The department in July 2025 also announced an additional 1,290 MW of solar projects as preferred bidders. We now await commercial and financial close of these projects.
View DetailsIs it working?
We await financial close from the winning bidders before construction and contribution to grid stability. While the bid window is never going to achieve its initial targets, we will continue to monitor those projects that were selected until they are contributing to the grid before changing the status of this delivery item to halted. Projects are expected to join the grid in October 2027 at the earliest.
Actions
All of the required actions for the BW7 round have been implemented, however the bid window failed to achieve its initial capacity target with only 54% of the capacity available from the preferred bidders. We now await the preferred bidders to conclude commercial and financial close and begin construction. Additional solar PV preferred bidders were announced in July to make up the shortfall of wind projects, with more expected in August to close the gap on the round's targeted MW.
Are there plans?
Yes, in line with IPP Office's bid window approach, the RFP was released in December 2023 and closed on 15 August 2024 after being extended from April. Preferred bidders were announced in December 2024. The delays were due to grid access constraints that made it difficult for some projects to secure access agreements with Eskom.
Is it on the agenda?
The procurement process for Bid Window 7 was launched by the IPP Office in December 2023 and Electricity and energy Minister Kgosientsho Ramokgopa announced preferred bidders a year later.
Goals
To increase renewable energy procurement through Renewable Energy Independent Power Producer's Programme, BW7 had a total 5,000MW capacity target, which if successful would make it the largest REIPPP round to date.
Summary
On 14 December 2023, the IPPO announced the release of the BW7 procurement round that seeks to procure 5GW of new renewables through 3.2GW of wind and 1.8GW of solar energy.
View DetailsIs it working?
To be determined. Bid submissions followed by financial close for the winners are the short-term goals, after which construction of plants and contributions to grid stability will determine substantive efficacy.
Actions
RFP released.
Are there plans?
The RFP was released in December closing on 15 August 2024.
Is it on the agenda?
This bid window seeks to procure 5GW of new renewables through 3.2GW of wind and 1.8GW of solar energy.
Goals
The deadline for receiving bids has been extended from 30 May 2024 to 15 August 2024.
Summary
On 14 December 2023, the IPPO announced the release of the BW7 procurement round that seeks to procure 5GW of new renewables through 3.2GW of wind and 1.8GW of solar energy.
View DetailsIs it working?
To be determined. Bid submissions followed by financial close for the winners are the short-term goals, after which construction of plants and contributions to grid stability will determine substantive efficacy.
Actions
RFP released.
Are there plans?
The RFP was released in December closing on 15 August 2024.
Is it on the agenda?
This bid window seeks to procure 5GW of new renewables through 3.2GW of wind and 1.8GW of solar energy.
Goals
The deadline for receiving bids has been extended from 30 May 2024 to 15 August 2024.
Summary
On 14 December 2023, the IPPO announced the release of the BW7 procurement round that seeks to procure 5GW of new renewables through 3.2GW of wind and 1.8GW of solar energy. The IPPO received 48 onshore wind and solar PV proposals totaling 10,218 MW).
View DetailsIs it working?
The bid window is in process with bid being assessed.
Actions
RFP Closed
Are there plans?
The RFP was released in December and closed on 15 August 2024.
Is it on the agenda?
This bid window seeks to procure 5GW of new renewables through 3.2GW of wind and 1.8GW of solar energy.
Goals
To increase renewable energy procurement through REIPPPP
Summary
On 14 December 2023, the IPPO announced the release of the BW7 procurement round that seeks to procure 5GW of new renewables through 3.2GW of wind and 1.8GW of solar energy. The IPPO received 48 onshore wind and solar PV proposals totaling 10,218 MW).
View DetailsIs it working?
The bid window is in process with bid being assessed.
Actions
RFP Closed
Are there plans?
The RFP was released in December and closed on 15 August 2024.
Is it on the agenda?
This bid window seeks to procure 5GW of new renewables through 3.2GW of wind and 1.8GW of solar energy.
Goals
To increase renewable energy procurement through REIPPPP
Summary
Of the 25 preferred bidders appointed, 11 projects are currently under construction. Fourteen projects did not reach financial close.
View DetailsIs it working?
The bid window has been completed. Of the 25 preferred bidders appointed, 11 projects are currently in construction. Fourteen projects did not reach financial close. Therefore, energy from this bid window is not yet on stream.
Actions
Connect to the grid once ready.
Are there plans?
To complete construction and connect to the grid.
Is it on the agenda?
Some projects are in construction, others waiting for financial close and
Goals
To increase renewable energy procurement through REIPPPP
Summary
Of the 25 preferred bidders appointed, two are currently operational and nine are under construction. Fourteen projects have not reached financial close and their preferred bidder status was terminated. The 25 appointed bidders totalled capacity of 2,583MW, close to target, but the 11 projects that reached financial close have capacity of 1,159MW. There was a long delay between bidding and announcement of successful projects and in this period global prices shifted dramatically in part due to the war in the Ukraine. It is not clear if any of the other projects may still reach financial close given they were no longer financially viable. Some projects have been resubmitted at updated prices under BW7.
View DetailsIs it working?
The bid window 5 procurement process has been completed. Of the 25 preferred bidders appointed, 11 projects reached financial close and two of these are operational. We expect therefore that this deliverable will only be partially fulfilled.
Actions
The bidding round was held in April 2021, and 25 bidders were selected with a combined capacity of 2 583 MW. However, there were extensive delays between reaching financial close and the announcement of preferred bidders. In the intervening period, the war in Ukraine and the Covid-19 pandemic led to a surge in global commodity prices that changed the financial viability of projects and rendered some unfeasible. The IPP Office then called the bid bonds on those which had not reached financial close (which would terminate the bids) though developers have refused to pay and are challenging these legally. Only two wind projects - 288 MW- have been operational since April 2025.
Are there plans?
The BW5 round was launched in 2021 and run by the IPP Office. Preferred bidders were named in 2022. Nine are still being constructed.
Is it on the agenda?
Yes, BW5 was a key part of rebooting the REIPPP programme, which was stalled in 2016.
Goals
To increase renewable energy procurement through Renewable Energy Independent Power Producer's Programme, BW5 had a target of procuring 2,600MW of new capacity - comprising of 1, 600 MW of onshore wind and 1,000 MW of solar PV.
Summary
Of the 25 preferred bidders appointed, two are currently operational and nine are under construction. Fourteen projects have not reached financial close and their preferred bidder status was terminated. The 25 appointed bidders totalled capacity of 2,583MW, close to target, but the 11 projects that reached financial close have capacity of 1,159MW. There was a long delay between bidding and announcement of successful projects and in this period global prices shifted dramatically in part due to the war in the Ukraine. It is not clear if any of the other projects may still reach financial close given they were no longer financially viable. Some projects have been resubmitted at updated prices under BW7.
View DetailsIs it working?
The bid window 5 procurement process has been completed. Of the 25 preferred bidders appointed, 11 projects reached financial close and two of these are operational. We expect therefore that this deliverable will only be partially fulfilled.
Actions
The bidding round was held in April 2021, and 25 bidders were selected with a combined capacity of 2 583 MW. However, there were extensive delays between reaching financial close and the announcement of preferred bidders. In the intervening period, the war in Ukraine and the Covid-19 pandemic led to a surge in global commodity prices that changed the financial viability of projects and rendered some unfeasible. The IPP Office then called the bid bonds on those which had not reached financial close (which would terminate the bids) though developers have refused to pay and are challenging these legally. Only two wind projects - 288 MW- have been operational since April 2025.
Are there plans?
The BW5 round was launched in 2021 and run by the IPP Office. Preferred bidders were named in 2022. Nine are still being constructed.
Is it on the agenda?
Yes, BW5 was a key part of rebooting the REIPPP programme, which was stalled in 2016.
Goals
To increase renewable energy procurement through Renewable Energy Independent Power Producer's Programme, BW5 had a target of procuring 2,600MW of new capacity - comprising of 1, 600 MW of onshore wind and 1,000 MW of solar PV.
Summary
Of the 25 preferred bidders appointed, 11 projects are currently under construction. Fourteen projects did not reach financial close.
View DetailsIs it working?
Not yet.Of the 25 preferred bidders appointed, 11 projects are currently in construction. Fourteen projects did not reach financial close.
Actions
Connect to the grid once ready.
Are there plans?
To complete construction and connect to the grid.
Is it on the agenda?
Some projects are in construction, others waiting for financial close and
Goals
To increase renewable energy procurement through REIPPPP
Summary
Of the 25 preferred bidders appointed, 11 projects are currently under construction. Fourteen projects did not reach financial close.
View DetailsIs it working?
Not yet.Of the 25 preferred bidders appointed, 11 projects are currently in construction. Fourteen projects did not reach financial close.
Actions
Connect to the grid once ready.
Are there plans?
To complete construction and connect to the grid.
Is it on the agenda?
Some projects are in construction, others waiting for financial close and
Goals
To increase renewable energy procurement through REIPPPP
Summary
Of the 25 preferred bidders appointed, 11 projects are currently under construction. Fourteen projects did not reach financial close.
View DetailsIs it working?
The bid window has been completed. Of the 25 preferred bidders appointed, 11 projects are currently in construction. Fourteen projects did not reach financial close. Therefore, energy from this bid window is not yet on stream.
Actions
Connect to the grid once ready.
Are there plans?
To complete construction and connect to the grid.
Is it on the agenda?
Some projects are in construction, others waiting for financial close and
Goals
To increase renewable energy procurement through REIPPPP
Summary
Of the 25 preferred bidders appointed, 11 projects are currently under construction. Fourteen projects did not reach financial close.
View DetailsIs it working?
The bid window has been completed. Of the 25 preferred bidders appointed, 11 projects are currently in construction. Fourteen projects did not reach financial close. Therefore, energy from this bid window is not yet on stream.
Actions
Connect to the grid once ready.
Are there plans?
To complete construction and connect to the grid.
Is it on the agenda?
Some projects are in construction, others waiting for financial close and
Goals
To increase renewable energy procurement through REIPPPP
Summary
According to the Department of Mineral Resources and Energy (DMRE), the first two out of six projects of Bid Window 6 of the government's procurement programme for renewable energy power reached financial close in April and are now in construction. The two solar projects are the Virginia Solar Park in the Free State and Doornhoek PV in the North West. Combined, they will contribute 360 MW of energy to the grid.
View DetailsIs it working?
The bid window has been completed with winners announced who must now reach financial close.
Actions
Support the BW6 projects to reach commercial close.
Are there plans?
To ensure that the remaining projects from Bid Window 6 proceed to commercial close.
Is it on the agenda?
To increase renewable energy procurement through REIPPPP.
Goals
To increase renewable energy procurement through REIPPPP
Summary
According to the Department of Mineral Resources and Energy (DMRE), the first two out of six projects of Bid Window 6 of the government's procurement programme for renewable energy power reached financial close in April and are now in construction. The two solar projects are the Virginia Solar Park in the Free State and Doornhoek PV in the North West. Combined, they will contribute 360 MW of energy to the grid.
View DetailsIs it working?
The bid window has been completed with winners announced who must now reach financial close.
Actions
Support the BW6 projects to reach commercial close.
Are there plans?
To ensure that the remaining projects from Bid Window 6 proceed to commercial close.
Is it on the agenda?
To increase renewable energy procurement through REIPPPP.
Goals
To increase renewable energy procurement through REIPPPP
Summary
According to the Department of Mineral Resources and Energy (DMRE), the first two out of six projects of Bid Window 6 of the government's procurement programme for renewable energy power reached financial close in April and are now in construction. The two solar projects are the Virginia Solar Park in the Free State and Doornhoek PV in the North West. Combined, they will contribute 360 MW of energy to the grid.
View DetailsIs it working?
The bid window has been completed with winners announced who must now reach financial close.
Actions
Support the BW6 projects to reach commercial close.
Are there plans?
To ensure that the remaining projects from Bid Window 6 proceed to commercial close.
Is it on the agenda?
To increase renewable energy procurement through REIPPPP.
Goals
To increase renewable energy procurement through REIPPPP
Summary
According to the Department of Mineral Resources and Energy (DMRE), the first two out of six projects of Bid Window 6 of the government's procurement programme for renewable energy power reached financial close in April and are now in construction. The two solar projects are the Virginia Solar Park in the Free State and Doornhoek PV in the North West. Combined, they will contribute 360 MW of energy to the grid.
View DetailsIs it working?
Not yet.
Actions
Support the BW6 projects to reach commercial close.
Are there plans?
To ensure that the remaining projects from Bid Window 6 proceed to commercial close.
Is it on the agenda?
To increase renewable energy procurement through REIPPPP.
Goals
To increase renewable energy procurement through REIPPPP
Summary
According to the Department of Mineral Resources and Energy (DMRE), the first two out of six projects of Bid Window 6 of the government's procurement programme for renewable energy power reached financial close in April and are now in construction. The two solar projects are the Virginia Solar Park in the Free State and Doornhoek PV in the North West. Combined, they will contribute 360 MW of energy to the grid.
View DetailsIs it working?
Not yet.
Actions
Support the BW6 projects to reach commercial close.
Are there plans?
To ensure that the remaining projects from Bid Window 6 proceed to commercial close.
Is it on the agenda?
To increase renewable energy procurement through REIPPPP.
Goals
To increase renewable energy procurement through REIPPPP
Summary
According to the Department of Mineral Resources and Energy (DMRE), the first two out of six projects of Bid Window 6 of the government's procurement programme for renewable energy power reached financial close in April and are now in construction. The two solar projects are the Virginia Solar Park in the Free State and Doornhoek PV in the North West. Combined, they will contribute 360 MW of energy to the grid.
View DetailsIs it working?
The bid window has been completed with winners announced who must now reach financial close.
Actions
Support the BW6 projects to reach commercial close.
Are there plans?
To ensure that the remaining projects from Bid Window 6 proceed to commercial close.
Is it on the agenda?
To increase renewable energy procurement through REIPPPP.
Goals
To increase renewable energy procurement through REIPPPP
Summary
According to the Department of Mineral Resources and Energy (DMRE), the first two out of six projects of Bid Window 6 of the government's procurement programme for renewable energy power reached financial close in April and are now in construction. The two solar projects are the Virginia Solar Park in the Free State and Doornhoek PV in the North West. Combined, they will contribute 360 MW of energy to the grid.
View DetailsIs it working?
The bid window has been completed with winners announced who must now reach financial close.
Actions
Support the BW6 projects to reach commercial close.
Are there plans?
To ensure that the remaining projects from Bid Window 6 proceed to commercial close.
Is it on the agenda?
To increase renewable energy procurement through REIPPPP.
Goals
To increase renewable energy procurement through REIPPPP