No data available for the deliverable: Increase in planned Eskom maintenance
No data available for the deliverable: Increase in planned Eskom maintenance
No data available for the deliverable: Increase in planned Eskom maintenance
Summary
Eskom conducted more planned maintenance on its power stations in 2024 than in the previous four years. This led to a downward trend in unplanned breakdowns since 2023.
Eskom has since decided to space out planned maintenance over longer horizons as opposed to concentrating it within shorter windows to ensure enough generation capacity is available to power the economy. It ran into a challenge in 2025, when units did not return to service on time following planned maintenance. These outage slips contributed to load shedding - Eskom is working to address the root causes.
Is it working?
Improving planned maintenance has reduced unplanned breakdowns and helped limit load shedding - with South Africa recording more than 180 days without load shedding by mid-November 2025.
Eskom by September 2025 recovered just under 7.8GW generation capacity through long term outage completions and new build (Kusile unit 6).
The Energy Availability Factor has improved from lows of 55% in 2023, and is so far consistently above 60% in the financial year 2025/26.
As of mid-November 15 of Eskom's generation units - equivalent to 5 645MW - are on cold reserve due to excess capacity.
Actions
Eskom is working to contain maintenance operations within prescribed timelines, and avoid outage slips that contributed to load shedding in winter 2025.
To do this it will work on achieving operational excellence - with Eskom putting a "systems, people, process mindset" in place across the organisation. This includes equipping managers better, ensuring there are enough staff resources at power stations, as well as addressing procurement challenges to secure parts in time for maintenance.
Most of the Generation recovery Plan objectives have been met- the focus is now on sustaining the recovery.
Are there plans?
Eskom's summer outlook outlined a plan to sustain recovery in generation performance so that the EAF can climb to 70%.
Planned maintenance is being smoothened out over longer horizons as opposed to shorter windows to ensure there is enough generation capacity available.
Eskom is still addressing the issue of outage slips.
Eskom is implementing a Demand Management Programme to also free up generation capacity and reduce load shedding.
Grid infrastructure network rollout, as per the Transmission Development Plan is also important to connect new generation projects and reduce load shedding.
Is it on the agenda?
Increasing planned maintenance is part of the energy action plan developed by the National Electricity Crisis Committee and will help Eskom achieve an energy availability factor (EAF) of 70%.
Goals
The planned maintenance programme, one of the objectives of the energy action plan, aimed to achieve a higher energy availability factor.
References
Departments / Govt Institutions
No data available for the deliverable: Increase in planned Eskom maintenance
No data available for the deliverable: Increase in planned Eskom maintenance
No data available for the deliverable: Increase in planned Eskom maintenance
No data available for the deliverable: Increase in planned Eskom maintenance
Summary
Electricity Minister Kgosientsho Ramokgopa says there are greater levels of stability at Eskom since the appointment of permanent CEO, Dan Marokane.
View DetailsIs it working?
Yes
Actions
CEO and board appointments
Are there plans?
No further plans
Is it on the agenda?
To restore stability to the power utility
Goals
0.00
Departments / Govt Institutions
Summary
Electricity Minister Kgosientsho Ramokgopa says there are greater levels of stability at Eskom since the appointment of permanent CEO, Dan Marokane.
View DetailsIs it working?
Yes
Actions
CEO and board appointments
Are there plans?
No further plans
Is it on the agenda?
To restore stability to the power utility
Goals
0.00
Departments / Govt Institutions
Summary
Electricity Minister Kgosientsho Ramokgopa says there are greater levels of stability at Eskom since the appointment of permanent CEO, Dan Marokane.
View DetailsIs it working?
Yes
Actions
CEO and board appointments
Are there plans?
No further plans
Is it on the agenda?
To restore stability to the power utility
Goals
0.00
Departments / Govt Institutions
Summary
Electricity Minister Kgosientsho Ramokgopa says there are greater levels of stability at Eskom since the appointment of permanent CEO Dan Marokane. The appointment of Eskom head of Generation, Bheki Nxumalo in 2023, has also been key to the recovery in performance of the utility's coal fleet.
View DetailsIs it working?
The appointment of a permanent CEO and a permanent head at Eskom's generation division has yielded improvements in performance of Eskom's coal fleet.The utility reported a profit for the first time in eight years, for the financial year-ended March 2025, which is also a testament to its financial and operational recovery.Eskom also announced seven new board appointments in mid-October, aimed at acquiring new skills to meet the changing needs of the entity while also ensuring continuity by retaining four board members.Mteto Nyati's term as board chair has not yet expired.Eskom also appointed a permanent CEO to the National Transmission Company of South Africa, Monde Bala.
Actions
Appointment of permanent head for Eskom Distribution still required, amid unbundling.Search for new CFO to replace Calib Cassim when he retires in October 2026 needed.
Are there plans?
CFO Calib Cassim is set to retire in October 2026 and Eskom is working on recruiting a successor. Advertisements are not yet out.
rnDistribution unbundling is still under way and requires a solution to municipal debt, which is still being tested.
rn
Is it on the agenda?
Appointment of new CFO expected to happen timeously.Appointment of permanent Distribution head tied to unbundling of the subsidiary which is still under way.Board has been timeously renewed.
Goals
To restore leadership stability at the power utility.
Departments / Govt Institutions
Summary
Electricity Minister Kgosientsho Ramokgopa says there are greater levels of stability at Eskom since the appointment of permanent CEO, Dan Marokane.
View DetailsIs it working?
Yes
Actions
CEO and board appointments
Are there plans?
No further plans
Is it on the agenda?
To restore stability to the power utility
Goals
0.00
Departments / Govt Institutions
Summary
Electricity Minister Kgosientsho Ramokgopa says there are greater levels of stability at Eskom since the appointment of permanent CEO, Dan Marokane.
View DetailsIs it working?
Yes
Actions
CEO and board appointments
Are there plans?
No further plans
Is it on the agenda?
To restore stability to the power utility
Goals
0.00
Departments / Govt Institutions
Summary
Electricity Minister Kgosientsho Ramokgopa says there are greater levels of stability at Eskom since the appointment of permanent CEO, Dan Marokane.
View DetailsIs it working?
Yes
Actions
CEO and board appointments
Are there plans?
No further plans
Is it on the agenda?
To restore stability to the power utility
Goals
0.00
Departments / Govt Institutions
Summary
Electricity Minister Kgosientsho Ramokgopa says there are greater levels of stability at Eskom since the appointment of permanent CEO, Dan Marokane.
View DetailsIs it working?
Yes
Actions
CEO and board appointments
Are there plans?
No further plans
Is it on the agenda?
To restore stability to the power utility
Goals
0.00
Departments / Govt Institutions
Summary
Eskom has achieved an Energy Availability Factor (EAF) of 70.78% (May 2024). This was last achieved nearly three years previously. Eskom increased the Generation Recovery Plan to improve plant performance, with support from private sector experts. Planned maintenance increased to more than 8,000MW over the summer period to enable improved performance going forward. Technical experts were employed at identified power stations to support the Generation Recovery Plan and improve plant performance.
View DetailsIs it working?
Effective - As of May 2024, Eskom's EAF has surpassed the 70% mark, with no load shedding since March 2024.
Actions
Increased planned maintenance plan at Eskom.
Are there plans?
From the end of March 2024, planned maintenance was reduced from 8,000 MW to 5,000 MW in April 2024 and around 4,000 MW in May. This effectively made 4,000 MW available to the grid for the 2024 winter peak season.
Is it on the agenda?
The government was targeting an average EAF of 65% by March 2024 as part of the energy action plan.
Goals
One of the objectives of the energy action plan is to achieve a higher energy availability factor.
Departments / Govt Institutions
Summary
Eskom has achieved an Energy Availability Factor (EAF) of 70.78% by May 2024. This was previously achieved nearly three years ago. However, the EAF had fallen below 60%. Eskom implemented the Generation Recovery Plan to improve plant performance, with support from private sector experts. It ramped up planned maintenance to more than 8,000MW over the summer months to enable improved performance in future. Technical experts were also deployed to problematic power stations to improve their performance. However, the latest EAF (May 2025) was still hovering at an average of 61%. The original 70% target has been renewed for Eskom's 2026 financial year.
View DetailsIs it working?
Largely effective but overall EAF fluctuates, sometimes below target. Eskom has managed to improve plant performance, reflected in an improved EAF. In August it indicated that over half of its 14 power stations operate at an EAF above 70%. Three stations performed above 90% and four operate above 60%. Load shedding remains a risk and as per its Winter plan limited it to Stage 2 in mid-May. The original 70% target has been renewed for the current financial year. According to a 1 August statement, outages stand at 8 525MW, the lowest level in recent history.
Actions
At its winter outlook briefing in May, Eskom Group CEO Dan Marokane explained the power utility would be changing its planned maintenance strategy - implementing it over longer horizons as opposed to shorter windows to ensure enough generation capacity is available to support the economy. Other actions such as the return of Medupi 4, the successful commercial operation of Kusile 5 and synchronisation of Unit 6, as well as ensuring Koeberg Unit 2's licence to operate for another 20 years are in place for Eskom to meet the 70% target.
Are there plans?
Eskom continues to implement its Generation Recovery Plan aimed at reducing unplanned breakdowns at power plants and being more strategic about how and when to implement long-term, planned maintenance. Eskom also planned for the addition of generation capacity in 2025, mainly from the return of Medupi Unit 4 following an explosion in 2021, the synchronisation and operation of Kusile Unit 5 and 6 and reviewing the decommissioning schedule of coal plants based on system requirements.
Is it on the agenda?
The EAF was incorporated into the National Electricity Crisis Committee's action plan as one element of addressing the wider electricity crisis.
Goals
To minimise load-shedding, one of the objectives of the energy action plan is to achieve a higher Energy Availability Factor (EAF) at Eskom (the percentage of time a power plant can produce electricity). The goal is to have an average EAF of 70% by March 2025.
Departments / Govt Institutions
Summary
Eskom's energy availability factor (EAF) has risen above 60% from lows of 55% in 2023 but still falls short of the 70% target. There have been occasions (more than 30) where EAF hit the 70% mark since April 2025, according to Eskom. The higher EAF has also meant reduced load shedding, with South Africa experiencing more than 180 days without load shedding by mid-November 2025.Improvements in Eskom's fleet have been attributed to Eskom's Generation Recovery Plan.
View DetailsIs it working?
Largely effective:
- EAF has remained consistently above 60%.
- Unplanned outages have reduced substantially, by 24%, for the period 1 April 2025-14 November 2025.
- The utility still relies on Open Cycle Gas Turbines to meet peak demand.
Actions
At its summer outlook briefing in September 2025, Eskom officials indicated that the power utility has breathing room of 4GW to work with to meet demand over the summer period. This includes 800MW from Kusile Unit 6 that achieved commercial operation in late September and Medupi Unit 4 which added 800MW to the grid in July 2025. Koeberg Unit 2 was also granted a 20-year licence extension in early November 2025, which would see it continuing to add approximately 900MW to the grid.Other measures include Eskom's demand management programme that will free up 2.4GW.
Are there plans?
Eskom has completed the majority of its targets outlined in the Generation Recovery Plan, aimed at reducing unplanned breakdowns at power plants and boosting plant reliability. It will now focus on sustaining the recovery with operational reliability.Interventions include:
- Improve outage planning and execution
- Execute key strategic projects such as refurbishment of mid-life stations, Koeberg's long-term operations, improve emissions reductions in coal fleet.
- Focus on people includes leadership development and a culture of excellence.
- The original 70% EAF target has been renewed for the current financial year.
Is it on the agenda?
The EAF was incorporated into the National Electricity Crisis Committee's action plan as one element of addressing the wider electricity crisis.
Goals
To minimise load shedding, one of the objectives of the energy action plan is to achieve a higher Energy Availability Factor (EAF) at Eskom (the percentage of time a power plant can produce electricity). The goal is to have an average EAF of 70% by March 2025. But this has been pushed out to March 2026.
Departments / Govt Institutions
Summary
Eskom's energy availability factor (EAF) has risen above 60% from lows of 55% in 2023 but still falls short of the 70% target. There have been occasions (more than 30) where EAF hit the 70% mark since April 2025, according to Eskom. The higher EAF has also meant reduced load shedding, with South Africa experiencing more than 180 days without load shedding by mid-November 2025.Improvements in Eskom's fleet have been attributed to Eskom's Generation Recovery Plan.
View DetailsIs it working?
Largely effective:
- EAF has remained consistently above 60%.
- Unplanned outages have reduced substantially, by 24%, for the period 1 April 2025-14 November 2025.
- The utility still relies on Open Cycle Gas Turbines to meet peak demand.
Actions
At its summer outlook briefing in September 2025, Eskom officials indicated that the power utility has breathing room of 4GW to work with to meet demand over the summer period. This includes 800MW from Kusile Unit 6 that achieved commercial operation in late September and Medupi Unit 4 which added 800MW to the grid in July 2025. Koeberg Unit 2 was also granted a 20-year licence extension in early November 2025, which would see it continuing to add approximately 900MW to the grid.Other measures include Eskom's demand management programme that will free up 2.4GW.
Are there plans?
Eskom has completed the majority of its targets outlined in the Generation Recovery Plan, aimed at reducing unplanned breakdowns at power plants and boosting plant reliability. It will now focus on sustaining the recovery with operational reliability.Interventions include:
- Improve outage planning and execution
- Execute key strategic projects such as refurbishment of mid-life stations, Koeberg's long-term operations, improve emissions reductions in coal fleet.
- Focus on people includes leadership development and a culture of excellence.
- The original 70% EAF target has been renewed for the current financial year.
Is it on the agenda?
The EAF was incorporated into the National Electricity Crisis Committee's action plan as one element of addressing the wider electricity crisis.
Goals
To minimise load shedding, one of the objectives of the energy action plan is to achieve a higher Energy Availability Factor (EAF) at Eskom (the percentage of time a power plant can produce electricity). The goal is to have an average EAF of 70% by March 2025. But this has been pushed out to March 2026.
Departments / Govt Institutions
No data available for the deliverable: Pathway to stabilising power supply and achieve higher Eskom EAF
Summary
One of the objectives of the energy action plan is to achieve a higher energy availability factor.
View DetailsIs it working?
Effective - As of May 2024, Eskom's EAF has surpassed the 70% mark.
Actions
Planned maintenance plan at Eskom.
Are there plans?
From the end of March 2024, planned maintenance was reduced from 8,000 MW to 5,000 MW in April 2024 and around 4,000 MW in May. This effectively made 4,000 MW available to the grid during the winter 2024 peak season.
Is it on the agenda?
The government was targeting an average EAF of 65% by March 2024.
Goals
Eskom has achieved an Energy Availability Factor (EAF) of 70.78% (May 2024).
Departments / Govt Institutions
Summary
Eskom has achieved an Energy Availability Factor (EAF) of 70.78% (May 2024). This was last achieved nearly three years previously. Eskom increased the Generation Recovery Plan to improve plant performance, with support from private sector experts. Planned maintenance increased to more than 8,000MW over the summer period to enable improved performance going forward. Technical experts were employed at identified power stations to support the Generation Recovery Plan and improve plant performance.
View DetailsIs it working?
Effective - As of May 2024, Eskom's EAF has surpassed the 70% mark, with no load shedding since March 2024.
Actions
Increased planned maintenance plan at Eskom.
Are there plans?
From the end of March 2024, planned maintenance was reduced from 8,000 MW to 5,000 MW in April 2024 and around 4,000 MW in May. This effectively made 4,000 MW available to the grid for the 2024 winter peak season.
Is it on the agenda?
The government was targeting an average EAF of 65% by March 2024 as part of the energy action plan.
Goals
One of the objectives of the energy action plan is to achieve a higher energy availability factor.
Departments / Govt Institutions
Summary
Eskom has achieved an Energy Availability Factor (EAF) of 70.78% (May 2024). This was last achieved nearly three years previously. Eskom increased the Generation Recovery Plan to improve plant performance, with support from private sector experts. Planned maintenance increased to more than 8,000MW over the summer period to enable improved performance going forward. Technical experts were employed at identified power stations to support the Generation Recovery Plan and improve plant performance.
View DetailsIs it working?
Effective - As of May 2024, Eskom's EAF has surpassed the 70% mark, with no load shedding since March 2024.
Actions
Increased planned maintenance plan at Eskom.
Are there plans?
From the end of March 2024, planned maintenance was reduced from 8,000 MW to 5,000 MW in April 2024 and around 4,000 MW in May. This effectively made 4,000 MW available to the grid for the 2024 winter peak season.
Is it on the agenda?
The government was targeting an average EAF of 65% by March 2024 as part of the energy action plan.
Goals
One of the objectives of the energy action plan is to achieve a higher energy availability factor.
Departments / Govt Institutions
Summary
National Treasury commissioned an independent assessment of all Eskom coal-fired power facilities to better understand their operational problems. Having received the VGBE report in September 2023, the electricity minister issued a 10-point plan which was drawn from the VGBE report. However, Eskom is resisting implementation as it believes some of the report's findings were incorrect.
View DetailsIs it working?
No - because Eskom is resisting implementation of the plan itself; however, there areas of overlap that Eskom was implementing anyway.
Actions
VGBE report completed but Eskom is resisting some recommendations. The minister has drawn 10 points from the VGBE report that he has put forward as recommendations. However, Eskom is resisting, challenging some VGBE findings.
Are there plans?
The 10-point plan is in place but being resisted by Eskom.
Is it on the agenda?
The 10-point plan was drawn from the VGBE recommendations: https://www.stateofthenation.gov.za/assets/downloads/eap-11-03-24_moe-vmoe-fin.pdf
Goals
The results and recommendations of the report were intended to strengthen Eskom's business plan and help its turnaround efforts. The goal has shifted slightly -- to implement the 10-point plan announced by Electricity Minister Kgosientsho Ramokgopa.
References
Departments / Govt Institutions
Summary
National Treasury commissioned an independent assessment of all Eskom coal-fired power facilities to better understand their operational problems. Having received the VGBE report in September 2023, the electricity minister issued a 10-point plan which was drawn from the VGBE report. Some of the recommendations overlap with interventions in the Generation Recovery Plan. However, Eskom believes some of the report's findings were incorrect and is not fully implementing the recommednations.
View DetailsIs it working?
Not yet fully in effect.
Actions
The minister has drawn 10 points from the VGBE report that he has set down as specific actions to be followed through. However, Eskom is challenging some VGBE findings. For now the actions are stalled amid contestation. However, some of the plan action items aligned with Eskom's own plans - like the Generation Recovery Plan - and so have been implemented.
Are there plans?
The 10-point plan is in place and but full implementation is being held up as Eskom belives some issues wer factually incorrect.
Is it on the agenda?
The report was put on the agenda by National Treasury and then the 10-point plan was drawn from the VGBE recommendations. Electricity and Energy Minister Kgosientsho Ramokgopa has said the report predates the appointment of a group executive for generation , who has implemented several initiaitves such as the Generation Recovery Plan to improve plant performance. https://www.stateofthenation.gov.za/assets/downloads/eap-11-03-24_moe-vmoe-fin.pdf
Goals
The recommendations of the report are intended to strengthen Eskom's business plan and help its turnaround efforts, as part of debt relief conditions from National Treasury. It was consolidated into a 10-point action plan announced by Electricity Minister Kgosientsho Ramokgopa.
References
Departments / Govt Institutions
Summary
National Treasury commissioned an independent assessment of all Eskom coal-fired power facilities to better understand their operational problems. Having received the VGBE report in September 2023, the electricity minister issued a 10-point plan which was drawn from the VGBE report. Some of the recommendations overlap with interventions in the Generation Recovery Plan. However, Eskom believes some of the report's findings were incorrect and is not fully implementing the recommendations.
View DetailsIs it working?
Interventions linked to the Generation Recovery Plan have seen an improvement in Eskom plant performance, with the energy availability factor above 60% by 2025. Eskom has also improved financial performance, reporting a profit for the first time in eight years for the year to end-March 2025.
Actions
The minister has drawn 10 points from the VGBE report that he has set down as specific actions to be followed through. However, Eskom challenged some of the VGBE findings. Some of the planned action items align with Eskom's own plans, like the Generation Recovery Plan. The majority of the objectives have been achieved, and Eskom is focusing on sustaining the recovery.
Are there plans?
The 10-point plan is in place and aligned to the Generation Recovery Plan.
Is it on the agenda?
The report was put on the agenda by National Treasury and then the 10-point plan was drawn from the VGBE recommendations. Electricity and Energy Minister Kgosientsho Ramokgopa has said the report predates the appointment of a group executive for generation, who has implemented several initiatives such as the Generation Recovery Plan to improve plant performance.
Goals
The recommendations of the report are intended to strengthen Eskom's business plan and help its turnaround efforts, as part of debt relief conditions from National Treasury.
References
Departments / Govt Institutions
Summary
National Treasury commissioned an independent assessment of all Eskom coal-fired power facilities to better understand their operational problems. Having received the VGBE report in September 2023, the electricity minister issued a 10-point plan which was drawn from the VGBE report. Some of the recommendations overlap with interventions in the Generation Recovery Plan. However, Eskom believes some of the report's findings were incorrect and is not fully implementing the recommendations.
View DetailsIs it working?
Interventions linked to the Generation Recovery Plan have seen an improvement in Eskom plant performance, with the energy availability factor above 60% by 2025. Eskom has also improved financial performance, reporting a profit for the first time in eight years for the year to end-March 2025.
Actions
The minister has drawn 10 points from the VGBE report that he has set down as specific actions to be followed through. However, Eskom challenged some of the VGBE findings. Some of the planned action items align with Eskom's own plans, like the Generation Recovery Plan. The majority of the objectives have been achieved, and Eskom is focusing on sustaining the recovery.
Are there plans?
The 10-point plan is in place and aligned to the Generation Recovery Plan.
Is it on the agenda?
The report was put on the agenda by National Treasury and then the 10-point plan was drawn from the VGBE recommendations. Electricity and Energy Minister Kgosientsho Ramokgopa has said the report predates the appointment of a group executive for generation, who has implemented several initiatives such as the Generation Recovery Plan to improve plant performance.
Goals
The recommendations of the report are intended to strengthen Eskom's business plan and help its turnaround efforts, as part of debt relief conditions from National Treasury.
References
Departments / Govt Institutions
Summary
Eskom has acknowledged the report recommendations but pointed out some inaccuracies the minister of electricity has issued a 10-point plan to respond to the VGBE recommendations https://www.stateofthenation.gov.za/assets/downloads/eap-11-03-24_moe-vmoe-fin.pdf The implementation of the 10-point plan as unveiled by the minister of electricity
View DetailsIs it working?
No- we expect some resistance from Eskom as they are not in full agreement with the report findings
Actions
10-point plan
Are there plans?
10-point plan implementation
Is it on the agenda?
10-point plan as announced by the minister of Electricity https://www.energize.co.za/article/ramokgopa-unveils-new-10-point-plan-eskom
Goals
National Treasury commissioned an independent assessment of all Eskom coal-fired power facilities to better understand their operational problems. The results and recommendations aim to strengthen Eskom's business plan and help its turnaround efforts.
References
Departments / Govt Institutions
Summary
Eskom has acknowledged the report's recommendations but pointed out some inaccuracies . The minister of electricity issued a 10-point plan to respond to the VGBE recommendations.
View DetailsIs it working?
No - we expect some resistance from Eskom as they are not in full agreement with the report findings.
Actions
VGBE report completed, government resisting some recommendations.
Are there plans?
The 10-point plan .
Is it on the agenda?
The 10-point plan: https://www.stateofthenation.gov.za/assets/downloads/eap-11-03-24_moe-vmoe-fin.pdf
Goals
National Treasury commissioned an independent assessment of all Eskom coal-fired power facilities to better understand their operational problems. The results and recommendations aim to strengthen Eskom's business plan and help its turnaround efforts.
References
Departments / Govt Institutions
Summary
National Treasury commissioned an independent assessment of all Eskom coal-fired power facilities to better understand their operational problems. Having received the VGBE report in September 2023, the electricity minister issued a 10-point plan which was drawn from the VGBE report. However, Eskom is resisting implementation as it believes some of the report's findings were incorrect.
View DetailsIs it working?
No - because Eskom is resisting implementation of the plan itself; however, there areas of overlap that Eskom was implementing anyway.
Actions
VGBE report completed but Eskom is resisting some recommendations. The minister has drawn 10 points from the VGBE report that he has put forward as recommendations. However, Eskom is resisting, challenging some VGBE findings.
Are there plans?
The 10-point plan is in place but being resisted by Eskom.
Is it on the agenda?
The 10-point plan was drawn from the VGBE recommendations: https://www.stateofthenation.gov.za/assets/downloads/eap-11-03-24_moe-vmoe-fin.pdf
Goals
The results and recommendations of the report were intended to strengthen Eskom's business plan and help its turnaround efforts. The goal has shifted slightly -- to implement the 10-point plan announced by Electricity Minister Kgosientsho Ramokgopa.
References
Departments / Govt Institutions
Summary
National Treasury commissioned an independent assessment of all Eskom coal-fired power facilities to better understand their operational problems. Having received the VGBE report in September 2023, the electricity minister issued a 10-point plan which was drawn from the VGBE report. However, Eskom is resisting implementation as it believes some of the report's findings were incorrect.
View DetailsIs it working?
No - because Eskom is resisting implementation of the plan itself; however, there areas of overlap that Eskom was implementing anyway.
Actions
VGBE report completed but Eskom is resisting some recommendations. The minister has drawn 10 points from the VGBE report that he has put forward as recommendations. However, Eskom is resisting, challenging some VGBE findings.
Are there plans?
The 10-point plan is in place but being resisted by Eskom.
Is it on the agenda?
The 10-point plan was drawn from the VGBE recommendations: https://www.stateofthenation.gov.za/assets/downloads/eap-11-03-24_moe-vmoe-fin.pdf
Goals
The results and recommendations of the report were intended to strengthen Eskom's business plan and help its turnaround efforts. The goal has shifted slightly -- to implement the 10-point plan announced by Electricity Minister Kgosientsho Ramokgopa.
References
Departments / Govt Institutions