Processes optimisation.

#REF!

September 15, 2025

Energy one stop shop

The Energy One Stop Shop (EOSS), formally launched  on 27 July 2023 by then Trade, Industry and Competition Minister Ebrahim Patel is in the ramp-up phase of a four-stage process designed to expedite the regulatory approvals needed for new projects involving self-generation and projects that will be connected to the local power grid. COMPLETED: We stopped…

read more >>

Environmental permit timeline

One of the objectives of the energy action plan is to reduce red tape for environmental authorisations. These measures have now been implemented and are having an effect. COMPLETE: We will no longer track this reform.

read more >>

Nersa registration timeline

The reform is now complete – Registration of new private generating projects with Nersa now takes an average of 19 days. COMPLETE: We will no longer track this reform.

read more >>

Land use authorisation timeline

Land-use authorisations now take 30 days instead of 90. This enables faster issuance of environmental impact assessments, ultimately speeding up the process of developing new renewable energy plants.

read more >>